How much deposit should I charge to avoid funding my customer's job?
Charge a deposit, or agree stage payments, that cover what you must pay out before the customer's next payment reaches you. On a materials-heavy job that means at least the materials you pay for before then. Anything less, and your business is funding the customer's job with its own cash until their payment arrives.
Nandi Khumalo runs Khumalo Steelworks, a fictional East London company that makes steel staircases, balustrades and gates for developers and building contractors, with turnover of R12 million. A developer's purchase order arrives for the staircases and balustrades on a new office block: R720,000 plus VAT, "100% payable 30 days after completion". The same morning, the steel merchant confirms the order and asks for payment before it cuts a single length.
This article shows how to size a deposit from the job's own cash flow, with the numbers for that order.
What should a deposit cover?
A deposit should cover the money you pay out on a job before the customer's next payment arrives. A deposit is money the customer pays before work starts, credited against the price. For most contractors, the outflows before the first payment are:
materials ordered for the job, often paid on order or within 30 days;
wages for the weeks of fabrication or installation before a stage is invoiced and paid;
subcontractors, equipment hire and transport you pay along the way.
Rule of thumb: divide what you pay out before the customer's next payment by the job price; that share is the deposit or stage payment you need.
Overheads such as rent and admin salaries are paid whether you take the job or not, so they are not what a deposit is for. The point is that the job itself should not drain cash the rest of the business needs.
Illustrative example: the office block staircases
With no deposit, the order has Khumalo Steelworks funding the job for about 86 days, peaking at R480,000; a 40% deposit cuts the peak to R192,000.
Assumptions:
Price R720,000 excluding VAT (R828,000 including VAT).
Steel, galvanising and fixings R288,000, paid in week 1.
Fabrication and installation wages R24,000 a week for 8 weeks: R192,000.
The balance is invoiced on completion and paid 30 days later. All amounts exclude VAT.
Deposit | Deposit amount | Most cash the business funds |
|---|---|---|
None | R0 | R480,000 |
25% | R180,000 | R300,000 |
40% | R288,000 | R192,000 |
50% | R360,000 | R120,000 |
What the numbers mean
For Khumalo Steelworks, 66.7% of the price, R480,000, goes out before the final payment comes in. Few customers will pay that much upfront, so a deposit alone is unlikely to stop the funding on this job.
A 40% deposit covers the steel exactly, so the customer's money buys the customer's steel.
Adding a 30% stage payment at the end of fabrication in week 6, paid on the day it is invoiced, cuts the most the business funds from R192,000 to R144,000. On 30-day terms it would arrive after completion and save nothing, so agree a short payment period for stage payments.
Retentions (a share of each payment held back until after completion) and a customer who pays late or fails make the funding longer and riskier; a deposit also limits what you lose if the customer cannot pay.
How do stage payments and deposits work for VAT?
The VAT part of whatever the customer pays is not yours to spend, so plan your cash on the VAT-exclusive amounts. The example ignores VAT timing: input VAT on the steel comes back only with your return, and VAT on the final invoice can fall due before the customer pays. VAT is charged at 15% (SARS VAT), so the 40% deposit on this order is R288,000 plus R43,200 VAT.
A deposit held as security is not treated as payment for VAT until you apply it to the price or it is forfeited (the proviso to "consideration" in section 1 of the VAT Act). Most contractor deposits are part payments credited against the price, and issuing an invoice for a deposit can fix the time of supply on its own (section 9(1)), so expect VAT to be due on the deposit in the period you invoice or receive it.
Where a contract for construction, manufacture, erection or assembly work provides for payment in stages as the work progresses, each payment is treated as a separate supply, made when the payment falls due, is received or is invoiced on its own, whichever comes first (VAT Act section 9(3)(b)).
Whether VAT is due when a deposit is invoiced or received depends on whether it is part of the price or security held, so agree the treatment with whoever does your VAT returns before you send the first deposit invoice. For why VAT can fall due before the customer pays, see why you pay VAT before your customer pays.
What if the customer will not pay a deposit?
If the customer will not pay a deposit, change the payment structure or the price rather than quietly funding the job. Options include:
a materials payment when the steel is delivered to your workshop or site, though customers often ask for proof of ownership or security for materials held off site;
stage payments at clear milestones, such as end of fabrication and end of installation;
shorter payment terms on the final invoice;
supplier credit, so your materials are not paid for before the customer's first payment;
a higher price that covers the cost of the cash you are tying up, if you do agree to fund it.
Main contractors and developers often set their own payment terms, so this is a negotiation, not a policy you can impose. If your customers are homeowners, check the consumer and home-building rules that apply to your trade before setting deposit terms. Funding customers' jobs is one of the ways a profitable business runs out of cash; why a profitable business can have no cash shows where that leads. ANM's page on how independent partner firms support contractors covers the wider picture.
Before you accept the next purchase order
Before you sign the next order or contract, check five things.
List the materials, subcontractors and hire for the job from your quote, and note when each must be paid from your supplier terms.
Add the wages for the weeks before the first stage can be invoiced, from your production schedule.
Divide that total by the job price to see the deposit or stage payment that would stop you funding it.
Read the payment clauses in the customer's order or contract, including any retention and the days to pay.
Put the agreed deposit, stage payments and their VAT treatment in writing before you order materials.
Figures checked against SARS publications and the VAT Act on 15 November 2026, for the VAT rules in force on that date.
This is general educational information, not advice for your business. ANM is not an accounting firm or registered tax practitioner; professional services are provided by independent partner firms.